- Gypsum board has to be installed vertically according to direction of metal stud.
- Butt joints have to be right in the center of metal stud.
- Butt joints have to be crisscrossed.
- Gypsum board should be installed using “S” screw with 25 mm size.
- Screws for butt joints should be at maximum distance of 200 mm.
- Screws for the center of gypsum board should be at maximum distance of 300 mm.
Aplus Stud Framed Partition
plus metal stud frame partition system is very lightweight, fire resistance, economical, and easy to install. This system consists of Aplus gypsum board installed using screws on Zincalume-coated metal stud frame and finishing using compound system on gypsum board joints to produce smooth and flat surface which is suitable for room design.
PARTITION FRAME made from ZINCALUME / GALVANIZED material with 0,50 or 0,60 mm thickness. Easy to install, efficient in usage because can be ordered according to desired length.
Spesification refer to ASTM A 653, C 645 dan C 840.
Important procedures that have to be done in gypsum
board installation on partition system: